Project schedule

 

1. 1. 2017

Project Kick-off

1. Q 2017

Development of systems for purchasing, securing, managing and evaluating EIRs.

2. - 3. Q 2017

Web development and implementation of functionalities.

2. - 4. Q 2017

Elaboration of methodologies for management, workflow, financial flows, negotiation strategy of EIRs purchase and others.

1. - 4. Q 2018 Signatures of contracts with suppliers of EIRs.

1. Q 2018 - 4. Q 2020

Purchase of EIRs for Member Institutions supported by OP VVV.

2020

Negotiation of EIRs purchase terms for the next period, possible gradual transition to OA.

2021 - 2022

Purchase of EIRs for Member Institutions expected to be supported from the state budget.

2021 - 2022

Operation of the center, possible further OA transitions, evaluations, suggestions for recommendations for the future function of the center.

2022

Negotiation of EIRs purchase terms for the next period.

31. 12. 2022

End of the EU project.

2022

Evaluation of the benefits of the CzechELib project.